Place geometric tolerance frames, datum symbols, ISO 1302 surface texture symbols, ISO 2553 weld symbols and hole callouts on mechanical drawings.
Before you start
- GDT, DATUMSYMBOL, SURFACEFINISH, WELDSYMBOL and SYMBOLEDIT need 2D drafting (any paid licence level).
- HOLECALLOUT reads the model through a drawing view, so it needs 3D modelling (core.3d).
- A drawing open. All tools are on Drawing > Engineering symbols.
Steps for a feature control frame
- Choose Drawing > Engineering symbols > GDT (
GDT, aliasFCF). - At
Characteristic <Position>:type one of: Position, Flatness, Straightness, Circularity, Cylindricity, Profileline, Profilesurface, Angularity, Perpendicularity, Parallelism, Concentricity, Symmetry, Circularrunout, Totalrunout. - At
Tolerance (e.g. 0.05, or dia 0.1 M for a diameter zone at maximum material):type the tolerance. UseLfor least material. - At
Datums in order (e.g. A;B;C(M)), or Enter for none:give up to three datums. Form tolerances take none, so this step is skipped. - At
Note above the frame (e.g. 4X), or Enter for none:add a note if needed. - Give
Point on the feature for the leader's arrow, or Enter for none:andPosition of the frame (its left end):.
A datum that no datum symbol defines yet is allowed, with a note.
Other symbols
| Command | Prompts |
|---|---|
DATUMSYMBOL (DATUM) |
Datum letter <next free>:, Point on the datum feature (the triangle):, Position of the letter's box:. I, O and Q are not used; a letter already on the drawing is refused. |
SURFACEFINISH (SURFTEXT) |
Process [Removal/Noremoval/Any] <Removal>:, Roughness (e.g. Ra 3.2), or Enter for none: (typing 3.2 reads as Ra 3.2), Production method (e.g. ground), or Enter for none:, All around [Yes/No] <No>:, then a leader point on the surface or Enter to stand the symbol on it, and the position. |
WELDSYMBOL (WELDSYM) |
Weld [Fillet/Squarebutt/Vbutt/Bevelbutt/Plug/Spot] <Fillet>:, Side [Arrow/Other/Both] <Arrow>:, Size (e.g. a5 or z7), Length (e.g. 50, or 3x50 (100) for intermittent welds), Site weld and all around [Field/Allaround/Both/None] <None>:, Point on the joint (the arrow):, Start of the reference line:. |
Arrow side welds go on the reference line, other side welds on the dashed line.
Editing a symbol
- Choose
SYMBOLEDIT(under the Hole callout arrow) and select the symbol. - At
Field to change as name=value, or Enter to finish:type changes, for exampletol=0.05,datums=A;B,letter=C,value=Ra 1.6,h=3.5(text height). An empty value clears an optional field.
| Field | Symbol | What it does |
|---|---|---|
extra=P 25 F |
frame | Adds the projected-zone sign with its height, free state F, tangent plane T, unequal U or statistical ST. |
allaround=1, allover=1 |
frame | Puts the circles on the leader's bend. |
lay= |
surface texture | parallel, perpendicular, crossed, multi, circular, radial or particulate. |
contour= |
weld | flush, convex or concave. |
tail= |
weld | Text after the fork, for example a process number such as 111. |
On a frame, composite= adds a second row (a composite frame): give the tolerance and datums separated by vertical bars, for example composite=dia 0.05 | A | B.
Hole callouts
- Choose Drawing > Engineering symbols > Hole callout (
HOLECALLOUT, aliasHOLENOTE). - At
Edge of a hole seen end-on in a view:click the hole's circle. - Click
Position of the callout:.
The note is read from the model: how many alike holes the view shows (4X), the diameter, THRU or the depth, and a counterbore or countersink. It is drawn with the depth, counterbore and countersink signs; LIST gives the words, for example C'BORE Ø11.00 x 6.40 DEEP. VIEWUPDATE reads it again when the model changes; a hole it no longer finds is named and the callout left as it was.
Example
A 4-hole flange:
DATUMSYMBOL, letterA, on the flange face.HOLECALLOUTon one hole:4X Ø9.00 THRU.GDT, Position,dia 0.2 M, datumsA, leader to the callout.
Tips and common mistakes
- Each symbol is one object: it moves, copies, plots, exports to DXF and PDF and undoes as one. EXPLODE keeps the lines and drops the meaning.
- SYMBOLEDIT does not edit hole callouts or inspection balloons; they come from the model and from INSPECTIONNUMBER.
Troubleshooting
| Message or symptom | What it means and what to do |
|---|---|
| ""…" is not a datum letter (A to Z, not I, O or Q)." | Choose another letter. |
| "Datum … is already on this drawing." | Each datum letter is used once per drawing. |
| "Hole callouts are read from the model; VIEWUPDATE reads them again." | Shown when SYMBOLEDIT picks a hole callout. |
| "Inspection balloons follow INSPECTIONNUMBER; renumber with it." | Shown when SYMBOLEDIT picks an inspection balloon. |
| "No change." | The field already had that value. |
Related
- Drafting standards and inspection numbering
- Model-based definition with PMI
- Weldments: joints, welds, caps and gussets
Related
- Making mesh bodies
- Mesh Studio: selecting points, edges and faces
- Mesh Studio: editing tools
- Mesh Studio: subdivision, modifiers and booleans
- Parametric modelling overview
- Creating a sketch
Still stuck? Open a support ticket or use Help, then Contact support in Stratal CAD.